While Installation of B-SURE™ SWR System ensure :
|
-
To cut SWR pipe straight .
-
To properly place the elastomeric ring in its groove.
-
To avoid over tightening of door cap.
-
To use pipe clips at proper spacing to align the pipe stack properly.
-
Appropriate water seal traps are used where ever necessary before connecting it to the main stack.
To use Perma-Fix solvent cement for socketed joints.
|
|
|
Rubber Ring Joints |
|
|
|
Cut pipe square to the required length |
Chamfer the edge of the pipe. Remove all burrs, dust and dirt |
Apply lubricant on the external surface of the pipe and on the elastomeric ring. |
|
|
|
Make sure the Sealing ring is placed correctly in the groove |
Push the pipe into the socket. |
Ensure 10 mm gap between the pipe end and the socket register for thermal expansion and contraction |
|
Solvent Welded Joint |
|
|
Cut pipe square to the required length |
All burrs and grease, if any, from the internal and external surfaces should be removed |
|
|
Apply solvent cement uniformly on the inner surface of fitting and outer surface of pipe |
Insert the pipe end into socket end & push it fully in. |
|
|
- Arrange the correct location of 'P'/'Q'/'S' trap and properly set on the floor finish, having firm base.
- The outlet of the trap should be left open during filling the sunken portion.
- Apply the lubricant on trap connector ring and on the outlet of IWC PAN.
- Push the outlet of IWC PAN into the trap Socket to make the joint.
|
|